Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the acf domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/html/codes/africaguinee22i/web/wp/wp-includes/functions.php on line 6170

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the wp-migrate-db domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /var/www/html/codes/africaguinee22i/web/wp/wp-includes/functions.php on line 6170
Projet de construction du poste 110/20 kv de Kissosso plateau et de réhabilitation des 61 postes maçonnes… (Rapport final) – Africa Guinee

Deprecated: advanced-ads-output-wrapper-options est obsolète depuis la version 2.0.0 ! Utilisez advanced-ads-wrapper-attributes-ad à la place. in /var/www/html/codes/africaguinee22i/web/wp/wp-includes/functions.php on line 6170

Deprecated: La fonction create_wrapper est obsolète depuis la version 2.0.0 ! Utilisez get_wrapper_attributes à la place. in /var/www/html/codes/africaguinee22i/web/wp/wp-includes/functions.php on line 6170

Projet de construction du poste 110/20 kv de Kissosso plateau et de réhabilitation des 61 postes maçonnes… (Rapport final)

edg_2

Deprecated: advanced-ads-output-wrapper-options est obsolète depuis la version 2.0.0 ! Utilisez advanced-ads-wrapper-attributes-ad à la place. in /var/www/html/codes/africaguinee22i/web/wp/wp-includes/functions.php on line 6170

Deprecated: La fonction create_wrapper est obsolète depuis la version 2.0.0 ! Utilisez get_wrapper_attributes à la place. in /var/www/html/codes/africaguinee22i/web/wp/wp-includes/functions.php on line 6170

Résumé exécutif

Ce rapport constitue le plan d’action de réinstallation des populations élaboré dans le cadre du projet de construction du poste 110/20kV de Kissosso Plateau et de réhabilitation et construction des 61 postes maçonnés(réhabilitation de 22 postes maçonnés existants et construction de 39 nouveaux postes maçonnés) dans le cadre de réhabilitation du réseau de distribution de Dixinn, conformément aux exigences de la législation guinéenne et la politique OP 4.12 de la Banque Mondiale.

Objectif et composantes

L’objectif principal du projet de construction du poste 110/20kV de Kissosso Plateau et de réhabilitation et construction des s 61 postes maçonnés de distribution de Dixinnest d’une part, rendre fiable l’alimentation et réduire les longueurs et les charges des départs aux postes de Matoto et de Ratoma et d’autre part améliorer la qualité des services de fourniture d’électricité.

L'atteinte de cet objectif devrait permettre à EDG d’améliorer la qualité de ses services à sa clientèle. 

Merci de lire ici l’intégralité du rapport final…

Créé le 26 février 2018 09:19

Nous vous proposons aussi

TAGS

étiquettes: ,

TOTAL

YELLOWBET

UBA

LONAGUI

SONOCO

AGB2G

CBG

smb-2

Consortium SMB-Winning

Annonces

Recommandé pour vous

Annonces